Construction of Small and Big Engineering Structures and Reinfrorced Concrete Works of the South Approach Viaduct at Gebze-Orhangazi-İzmir Highway Gebze-Orhangazi 4.Region ,Bursa-İzmit
Client
: Nurol İnşaat ve Ticaret A.Ş.
Contract Date
: 2012
Final Completion
: 2013
Contract Value
: 4.972.699 TL
Within the scope of the Project, the construction of small and big engineering structures, the reinforced concrete Works of the abutments of the South Aprroach Viaduct andfoundations of the 11  middle pier, production of guide walls and the setting of the reinforcing cages of the diaphragm wall is going to be completed.


PRODUCTION;

As part of the Project;
- 55.000 m3 of concrete 
- 60.000 m3 excavation
- 8.000 tons of iron