Bağıştaş 1 Dam and HEPP Project
Client
: IC İÇTAŞ İNŞAAT SANAYİ ve TİCARET A.Ş.
Contract Date
: 2012
Final Completion
: 2013
Contract Value
: 11.336.812 TL
Within the scope of the Project the following Works are being conducted;
- Form, concrete and iron works of the Central Building (height: 46 m), tailwater canal, stilling basin, power conduit and discharge canal.
-Construction of 5  TCDD displaced bridges (total length: 900 m, height :32 m) - Final concrete pouring of T1 Tunnel 
- Fabrication and installation of the prefabricated beams of the spillway and intake structure.


PRODUCTION

120.000,00 m2 of  form 
 150.000,00 m3 of concrete
 9.000,00 tons of iron
 80.000,00 m3 excavation 
 5.000,00 m bored pile production (Ǿ 120 )
 162 pre tensioned bridge girder production and installation
 240 nonprestressed bridge girder production and installation