Construction of the Reallocation Roads of Kandil Dam and HEPP - Kandil
Client
: ENERJİSA ENERJİ ÜRETİM A.Ş.
Contract Date
: 2011
Final Completion
: 2013
Contract Value
: 27.918.871 TL
As part of the Project the reconstruction and enhancement of the reallocated roads ( excavation,filling,rigging, foundation surface treatment with bitumen hot mix etc,total length of the roads: 22 km) is being implemented.Also the construction of 2 viaducts (total length: 465 m,total height: 92 m), headwalls, retaining walls, trench work, drainage and mason wall manufacturing, and roadway railing for heavy services is going to be completed.

PRODUCTION

Within the scope of the project ;
Excavation :  1.600.000 m3
Filling :  1.300.000 m3
Regulating : 24,00 km
Surface Treatment : 200 decare
Base and Sub-base: 100.000 tons 
Masonry Wall : 25.000 m3
Concrete production : 30.000 m3
Iron manufacturing and installation: 3.500 tons
Pre-tensioned bridge girder production and installation : 105 
(The installation of the bridge girders was done by  ’’ launching girder ’’)
Heavy-duty guard rail at bridges : 1.100 m
Pedestrian guard rail : 1.100 m