Marmaray Project - BC1 Agreement, Yenikapı Tube Tunnel Station, Production of the Form, Iron, Concrete and the Cooing Pipe Works Regarding the Permanent Construction Works and the Ventilation Structure - İstanbul
At Marmaray Project, as one of the most important infrastructure transportation projects around the world and the ’ Project of the Century’ as called in Turkey, the productions of the concrete, iron,form works and the installation of the cooling pipes ,which are work items of BC-1 Railway Bosphorus Passing, Tunnels and Stations Work Category and under the definitons of Ventilation Building and Permanent Construction Works ; completed succesfully and timely.The construction area of the buildings is 14.000 m2 and they have height of 18 m.
PRODUCTION
Within the scope of the project ;
- 65.000,00 m3 bof concrete
- 105.000 m2 of form
- 9.500 tons of iron
- 160.000 m3 of supporting scaffolding
- 90.000 m. cooling pipe installlation
were conducted.